摘要
混凝土高坝往往有一二百层,仿真应力分析的计算量十分庞大。笔者提出的并层算法使计算得到极大简化,但当坝内纵横接缝较多时,并层的效果有所降低。本文提出一种特殊的接缝单元,使各坝块可独立进行并层,互不影响,有效地解决了设有纵横接缝的混凝土高坝的仿真应力分析问题。
As there are 100-200 layers. in a high concrete dam, it is difficult to compute the stresses in the dam simulating the process of construction. The computation is simplified remarkably by the writer's mixed-layer method in ref[1]. But the degree of simplification is reduced when there are many longitudinal and transverse joints in the dam. Special 2D and 3D joint elements for stress field and temperature field are proposed in this paper. After introduction of these joint elements, the layers of construction may be combined independently in each block of the dam. Thus the computation of stresses and temperatures simulating construction process in high concrete dams with longitudinal and transverse joints is simplified a great deal.
出处
《水力发电学报》
CSCD
北大核心
1995年第3期14-21,共8页
Journal of Hydroelectric Engineering
基金
国家自然科学基金
长江三峡建设总公司和国家攀登计划的资助
关键词
混凝土高坝
并层算法
接缝单元
应力
Concrete dam Mixed-layer method Special joint elements