变顶高尾水洞的顶坡及体形设计方法 被引量:2

Method on Upper Ceiling and Configuration Design of Tailrace Tunnel with Inclined Ceiling
下载PDF
导出
摘要 基于机组甩负荷工况下变顶高尾水系统尾水管进口处真空度的计算公式,推导出保证尾水管进口满足真空度要求的顶坡计算分析公式。在机组甩负荷后明渠最大负涌浪以及安全顶坡分析公式的基础上,提出了变顶高尾水洞体形设计的程序性定量化方法,从而可对变顶高尾水洞的体形进行定量化的分析设计。由顶坡坡度分析公式所获得的计算结果与物理模型实验结果进行了比较,表明该公式是合理的。这些结果和方法可以方便地应用于工程初步设计。 The formula for the upper ceiling slope analysis of a tailrace tunnel with inclined ceiling was deduced from the formula for vacuum degree calculation in the draft-tube inlet of such tailrace tunnel under the condition of turbine load rejection.A procedural and quantitative method for the configuration design of tailrace tunnel with inclined ceiling was presented on the basis of upper ceiling slope analysis formula and maximum negative surge of open channel under the condition of turbine load rejection.The comparison between the results obtained from the upper ceiling slope analysis formula and model experiments show that the formula is reasonable.The results and methods can be easily applied to the preliminary design of tailrace tunnel with inclined ceiling.
出处 《水力发电》 北大核心 2010年第11期27-29,共3页 Water Power
基金 国家自然科学基金项目(50539070) 清华大学自主科研计划项目(2009THZ07060) 973项目(2006CB403304)
  • 相关文献

参考文献6

二级参考文献9

  • 1潘家铮.水工建筑物设计丛书(水工隧洞和调压室)[M].北京:水利电力出版社,1992..
  • 2薛阿强 罗禹权 等.三峡地下电站变顶高尾水洞方案(一机一洞)水力过渡过程试验研究报告[M].武汉:长江科学院,2000..
  • 3团体著者,水电工程规划设计土木工程导则.2,1990年
  • 4团体著者,水力学.下,1979年
  • 5薛阿强,三峡地下电站变顶高尾水洞方案1一机一洞)水力过渡过程试验研究报告,2000年
  • 6潘家铮,水工建筑物设计丛书.水工隧洞和调压室,1992年
  • 7华东水利学院,水电站,1980年
  • 8GB/T96 5 2 1 1997 水轮机调速器与油压装置技术条件
  • 9杨建东,陈鉴治,陈文斌,李世熙.水电站变顶高尾水洞体型研究[J].水利学报,1998,29(3):9-12. 被引量:14

共引文献26

同被引文献71

引证文献2

二级引证文献30

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部