摘要
结合工程实际情况,对羊泉灌区倒虹吸工程主要工序项目的施工方法进行细致安排优化改进,为工程的良好运行奠定了坚实的基础。
In combination with the actual project situation,the construction methods of the main process items of Yangquan Irrigation District's inverted siphon project are carefully arranged and improved.By these technical measures,the good basis for works' operation is established.
出处
《山西水利科技》
2012年第1期48-49,56,共3页
Shanxi Hydrotechnics
关键词
羊泉灌区
倒虹吸工程
施工方法
Yangquan Irrigation District
inverted siphon project
construction method