简介三峡VGS机组总装及盘车工艺的特点及其应用与改进,为后续机组的施工提供借鉴。
Fourteen generating units are installed in the left bank powerhouse of Three Gorges Hydropower Station. Six of them are made by the joint venture of VOITH, GE and SIEMENS. In unit assembling and aligning processes, many significant technical improvements are made for adapted to the site construction. The period of the unit installation has been shortened.
出处
《水电站机电技术》
2005年第4期1-2,12,共3页
Mechanical & Electrical Technique of Hydropower Station
关键词
三峡
VGS机组
总装及盘车
工艺改进
Three Gorges
VGS units
assembly and alignment
technical improvement