摘要
2号高炉的建设及投产,充分吸取了本厂前两座高炉设计、建设及投产过程的经验教训。对各种不合理的设备工艺环节进行了全面彻底的改造,为高炉顺利投产达产奠定了坚实基础。
The construction of the No.2 blast furnace in south area of Tanggang iron making plant has assimilated the experience and lesson during the construction of the former two blast furnaces. The innovation to the whole reasonless processes settled the massive base to the putting the blast furnace into production successfully.
出处
《冶金信息导刊》
2005年第4期19-21,共3页
Metallurgical Information Review