摘要
主要介绍了大朝山水电站水轮发电机转子现场装配工艺过程和质量控制,以及施工装配中遇到的实际问题和采取的处理措施,确保了转子装配的质量和施工进度,可供大型发电机转子现场装配时参考。
Technological progress and quality control for in-situ assembling of generator rotor at Dachaoshan hydropower station is described . Actual problems encountered in construction and assembling and measures taken are presented .Rotor assembling quality and construction schedule are ensured. These experiences are used for reference for large scaled generator rotor assembling in-situ .
出处
《四川水力发电》
2005年第4期59-61,67,共4页
Sichuan Hydropower
关键词
大朝山水电站
转子
装配
质量控制
问题处理
Dachaoshan hydropower station
rotor
assembling
quality control
handling problems