广西电网黑启动方案应注意的问题

Mentioned Problems about Black Start-up Plan in Guangxi Electric Power Grid
下载PDF
导出
摘要 为了在广西电网发生事故时能在尽可能短的时间内按照《广西电网黑启动方案》恢复供电,提出了水电厂及变电站黑启动应注意的问题:水电厂应在油罐中剩余油压尚能满足操作要求的情况下,尽快恢复水轮机的运转及恢复厂用电;变电站在全停电最初1 h内做好相应的恢复供电操作,根据电源的容量预测切掉一些不重要的负荷线路,使电源恢复后变电站能自动来电,恢复正常操作。 In order to recover operation after network accident as soon as possible according to “Black Startup Plan of Guangxi Electric Power Grid”, mentioned problems are pointed our about black start-up at hydroelectric power station and substation: Rotation of hyduaulic turbine and house service power has to be recovered immediately when the residual oil pressure in the tank will yet be sufficient for operation; in substation, with in the first black hour, related operation procedure has to be prepared, and such outlines as not so important has to be cut off according to forecasted automatically as soon as the power incoming power capacity, so that source comes again. normal power supply may be recovered
出处 《广西电力》 2005年第4期16-17,41,共3页 Guangxi Electric Power
关键词 电网 黑启动 水电厂 变电站 black start-up plan power network, power supply operation
  • 相关文献

参考文献4

  • 1江平,张宁,岳军,李林峰.广西电网黑启动方案研究[J].广西电力,2003,26(4):8-9. 被引量:8
  • 2.美、加停电事件对我国电网安全管理的四个启示[EB/OL].http:∥www.jcepc.com.cn/mjtd/cgqs.htm,.
  • 3.周孝信等四院士解析美加大停电事故对我们的启示[EB/OL].www.jcepc.com.cn/mjtd/ysjx.htm,.
  • 4DL5044-1995.火力发电厂、变电所直流系统设计技术规定[S].[S].,..

共引文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部