摘要
由于目前国内对预制节段拼装梁的设计、施工缺乏经验,介绍了广州市轨道交通四号线节段拼装梁的设计方法,包括结构设计、接缝处理、剪力键设置、安全系数选取和预应力施加等问题,对今后同类轨道梁的设计、施工及质量控制具有较强的参考价值。
Owing to the serious lack of experience in design & construction of pre-cast segmental box beams at home at present,this paper presents some design methods for pre-east segmental box beams of the 4th Guangzhou Metro Line,including its construction design, joint disposal, shear key setting, safety factor selecting and pre-stressing. It may serve as a reference for similar railway beams in design, construction and quality control.
出处
《国防交通工程与技术》
2005年第3期19-21,共3页
Traffic Engineering and Technology for National Defence
关键词
节段拼装
轨道交通桥梁
桥梁设计
assemble segmental box beams
metro bridge
design of bridges