对宝钢大型高炉的开炉操作经验进行了总结。认为大型高炉的开炉投产,是一项复杂、繁琐的系统工程, 根据工程项目建成时间合理有序地安排设备调试、热风炉烘炉、高炉开炉等工作,可以按预定计划完成高炉开炉,并取得最佳的经济效益。
The paper summarizes the startup preparation and operation practice of large sized blast furnace in Baosteel. The author thinks that startup operation of large sized blast furnace is a complicated work involving a lot of trivial activities. However, rationally and orderly arrangement of equipment commissioning, hot blast stove baking and startup preparation of blast furnace based on the project construction schedule are conducive to realize successful startup of blast furnace as scheduled and can result in the best economic benefit. The startup operation experience of large sized blast furnace in Baosteel is a good reference to the similar blast furnaces in China.
出处
《炼铁》
北大核心
2005年第B09期50-53,共4页
Ironmaking