摘要 介绍了葡萄牙Panasque ira钨矿房柱法采场地压现状,分析了空场中顶板和矿柱冒落破坏的原因,提出该矿采取防范地压的措施:对面积较大的采场,可在采场中预留宽度为11 m的隔离矿柱,以阻隔已采完但未冒落的空场,并尽可能使隔离矿柱与大断层平行,同时采取人工强制放顶与减小爆破药量等辅助措施,从而降低大面积冒落的危害。 The current status of the ground pressure in the stops using room and pillar mining in Panasqueira Wolframe Mine, Portugal is presented. Based on the analysis of the causes for the failure of roofs and pillars in the excavated area, it is proposed that the measures for this mine can be: for larger stopes, 11 m wide barrier pillars should be preserved to protect the stope that is excavated but hasn't caved-in, which should be made as parallel as possible to the main fault. Meanwhile, some auxiliary measures should be taken to reduce the danger of large area cave-in.
出处 《金属矿山》 CAS 北大核心 2005年第10期24-26,50,共4页 Metal Mine
关键词 地下开采 地压 矿柱 顶板 稳定性 效益 地压活动 葡萄牙 钨矿 治理 Underground mining, Ground pressure, Ore pillar, Roof, Stability
  • 相关文献

参考文献4

  • 1Mello Menddes F,Correira de Sa A,Ferreira e Silva J. The Geomechanics of Panasqueira mine, Portugal. 6th Congress of the International Society for Rock Mechanics, Proceedings / Comptes-rendus.Berichte -Montreal, Canada,1987.
  • 2Dinis da Gama C, 余贤斌. Geomechanical investigations in a multiple room and pillar mine.ISRM 9Th International Congress on Rock Mechanics.Paris / France ,1999.
  • 3余贤斌,Dinis da Gama C. Stability analyses of underground room and pillar stope by means of convergence, A Geotecnia Portuguesa e os Desafios do futuro.8th Congresso Naconal de Geotecnia.Lisboa, Portugal,2002.
  • 4宦秉炼,C.DinisDaGama.葡萄牙帕纳什凯拉黑钨矿采矿系统的改进[J].金属矿山,2000,29(2):19-22. 被引量:3

二级参考文献1

  • 1F Mellomendes,A Correin De Sa and J Ferreira E Silva.The geomechanics of Panasqueira Mine, porlugal[]..1987

共引文献2

同被引文献15