芙蓉水库库内引水对水库发电效益的影响研究 被引量:1

Study on Impact of Diverting Water from Furong Reservoir on Power Generation Effect of Furong Hydropower Station
下载PDF
导出
摘要 通过对2008、2020年两个城市供水水平年的库内引水方案进行调度图的设计和调节计算保证出力、相应保证率和多年平均年发电量3项指标,最终确定引水后对芙蓉水电站发电效益的影响。 Through power dispatching diagram design based on the scheme of diverting water from reservoir in two design level years of 2008 and 2020 for urban water supply and by analysis on the three indexes in regulation calculation, i.e. , dependable output, corresponding dependability and perennial average power yield, the impact of diverting water from the reservoir is finally ascertained on power generation effect of Furong Hydropower Station.
作者 吴文波
出处 《水利科技与经济》 2005年第8期500-501,共2页 Water Conservancy Science and Technology and Economy
关键词 库内引水 保证出力 发电量 发电水头 diverting water from reservoir dependable output power yield productive head
  • 相关文献

参考文献1

  • 1浙江省水利水电勘测设计院.浙江芙蓉水库工程初步设计报告[R].杭州:浙江省水利水电勘测设计院,2002.

同被引文献4

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部