Research on the fully fuzzy time-cost trade-off based on genetic algorithms 被引量:1

Research on the fully fuzzy time-cost trade-off based on genetic algorithms
下载PDF
导出
摘要 It is very difficult to estimate exact values of time and cost of an activity in project scheduling process because many uncertain factors, such as weather, productivity level, human factors etc. , dynamically affect them during project implementation process. A GAs-based fully fuzzy optimal time-cost trade-off model is presented based on fuzzy sets and genetic algorithms (GAs). In tihs model all parameters and variables are characteristics by fuzzy numbers. And then GAs is adopted to search for the optimal solution to this model. The method solves the time-cost trade-off problems under an uncertain environment and is proved practicable through a giving example in ship building scheduling. It is very difficult to estimate exact values of time and cost of an activity in project scheduling process because many uncertain factors, such as weather, productivity level, human factors etc. , dynamically affect them during project implementation process. A GAs-based fully fuzzy optimal time-cost trade-off model is presented based on fuzzy sets and genetic algorithms (GAs). In tihs model all parameters and variables are characteristics by fuzzy numbers. And then GAs is adopted to search for the optimal solution to this model. The method solves the time-cost trade-off problems under an uncertain environment and is proved practicable through a giving example in ship building scheduling.
出处 《Journal of Marine Science and Application》 2005年第3期18-23,共6页 船舶与海洋工程学报(英文版)
基金 Supported by the National High-Tech. R&D Program for CIMS (NO. 2003AA414060).
关键词 模糊数学 运算法则 数学理论 关系方程 fuzzy sets ranking fuzzy number genetic algorithms time-cost trade-off
  • 相关文献

参考文献2

二级参考文献13

  • 1刘泉宝,刘永清.基于网络计划技术的决策分析[J].系统工程,1994,12(1):29-25. 被引量:4
  • 2廖正环.道路施工组织与管理[M].北京:人民交通出版社,1996..
  • 3(美)J D惠斯特 葛震明(译).统筹方法管理指南[M].北京:机械工业出版社,1983..
  • 4Cadenas J M, Verdegay J L. Using ranking functions in multiobjective fuzzy linear programming [J]. Fuzzy Sets and Systems, 2000, 111:47-531.
  • 5Maleki H R, Tala M, Mashinchi M. Linear programming with fuzzy variables [J]. Fuzzy Sets and Systems,2000,109, 21-33.
  • 6Leu Sou-sen, Chen An-ting, Yang Chung-huei. A GA-based fuzzy optimal model for construction time-cost trade-off[J]. International Journal of Project Management, 2001,19 : 47-58.
  • 7Tang J, Wang D, Fung R Y K. Modeling and method based on GA for nonlinear programming problems with fuzzy objective and resources [J]. International Journal of System Science, 1998, 29(8):907-913.
  • 8Buckley James J, Feuring Thomas. Evolutionary algorithm solution to fuzzy problems:fuzzy linear programming[J]. Fuzzy Sets and Systems,2000(109) :35-53.
  • 9Chen S H. Ranking fuzzy numbers with maximizing set and minimizing set [J]. Fuzzy Sets and Systems, 1985,17:113-129.
  • 10Kim K, Park K S. Ranking fuzzy numbers with index of optimism [J]. Fuzzy Sets and Systems, 1990, 35 : 143-150.

共引文献10

同被引文献3

引证文献1

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部