三峡三期大坝工程大体积温控技术综述 被引量:7

Overeview of the technology of temperature control of massive body of the third phase work in Three Gorges project
下载PDF
导出
摘要 葛洲坝集团公司在三峡三期大坝工程大体积混凝土施工中加强过程控制,采用优化减水剂参量、采用低热水泥和高效减水剂控制出机口温度,供料浅降温、仓面降温和保温,通冷水等。并应用新材料、新工艺,实行精细化管理,从2003年8月开工至今,浇筑了200万m 3大体积混凝土未出现一条裂缝,保证了施工质量。 In the dam massive concreting of the phase-three work of the Three Gorges project, the China Gezhouba Group Co. exercised an intensive process control. It used an optimized amount of water reducing agent and low heat cement and high efficiency water reducing agent at the discharge port, heat reduction of the feed, placement and warm keeping and provision of cold water. Besides, adoption of new materials, technology and refined management had also been the cause of the high quality of construction work. From August, 2003 up to present. About 200 million cure of massive concrete have been placed without any cracks.
出处 《水力发电》 北大核心 2005年第10期14-16,27,共4页 Water Power
关键词 大体积混凝土 温控技术 三峡三期大坝 massive concrete temperature control technology three phase work of the dam
  • 相关文献

同被引文献53

引证文献7

二级引证文献134

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部