期刊文献+

三峡工程古树岭人工碎石加工技术 被引量:1

Crushing technology of artificial gravels at Gushuling of Three Gorges project
下载PDF
导出
摘要 古树岭人工碎石加工系统是三峡水利枢纽工程特大型粗骨料基地,主要承担三峡左岸一、二期工程1934万m 3混凝土所需粗骨料的生产任务,是当时国内外水电建设史上最大的人工碎石加工系统。由长委设计院与葛洲坝集团联合设计,葛洲坝集团承建施工、运行。在系统生产能力分析、应用新技术及研究人工砂中云母脱除工艺等方面都积累了宝贵的经验,可为借鉴。 The crushing man-made gravel crushing system is the extra-large course aggregate base of the Three Gorges project, providing aggregates for 19.34 million cu.m of concrete required by the 1 st and 2nd stage works on the left bank. It was then the largest man-made gravel crushing system in the hydropower history in the world. It was designed jointly by the Design Institute of the Yangtze river Planning Commission and the China Gezhouba Group Corp. constructed and operated by the China Gezhouba Group Corp. It has gained rich experiences in production caapacity analysis application of new teehnology and removal of mica from the manmade sands, which can be applicable to the other projects.
作者 兰芳
出处 《水力发电》 北大核心 2005年第10期50-52,共3页 Water Power
关键词 人工碎石加工 工艺流程 破碎设备 新技术 三峡工程 artificial gravel flow of workmanship crushing equipment new technology Three Gorges project
  • 相关文献

同被引文献6

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部