摘要 根据工程风险评价的基本原理,针对水下盾构隧道施工的特点,提出了一种可以对水下隧道工程的施工风险进行定级评估的方法,其主要原理是将定性和定量结合起来,正确定位各个风险因素,从而指导风险控制和管理.并以长江隧道工程为例,阐述了R=P×C风险定级法的具体应用. Based on the keystone of the engineering risks assessment, the characteristics of underwater shield tunnel construction are studied. The method of how to assess grade for the construction risks of underwater shield tunnel project is proposed. The main principle of the method is to combine the qualification with quantification, then localize every rick factor and guild the risk control and management. Changjiang underwater shield tunnel project is taken as an example to elucidate the idiographic application condition of R=P×C level assessment of risks method.
作者 吴贤国 王锋
出处 《华中科技大学学报(城市科学版)》 CAS 2005年第4期44-46,57,共4页 Journal of Huazhong University of Science and Technology
关键词 风险评价 模糊综合评价 风险定级 盾构隧道 施工风险 risks assessment blur integrated assessment level assessment of risks construction risk
  • 相关文献

参考文献1

二级参考文献5

  • 1王新洲,工程测量,1996年,2期,10页
  • 2团体著者,土地科技成果精选,1995年
  • 3严星,城市地产评估,1993年
  • 4冯保成,模糊数学实用集粹,1991年
  • 5谌作霖,土地管理技术,1991年

共引文献17

同被引文献256

引证文献40

二级引证文献406

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部