松江河梯级双沟水电站大坝导流采取一次拦断河床,隧洞导流的方式,工程施工期间,大量冰块将通过导流洞排泄。通过模型试验及吸收有关工程成功经验,采取措施,保证了施工期导流建筑物安全行凌渡汛。
The tunnel diversion for once damming dam is adopted in the construction of Songjianghe river cascade Shuanggou water power station A large number ice is discharged through the diversion tunnel during the engineering construction. The measures are adopted to guarantee the pass ice and flood discharging in construction period according To model test and project experience.
出处
《东北水利水电》
2005年第12期19-21,共3页
Water Resources & Hydropower of Northeast China
关键词
双沟水电站
导流隧洞
渡凌措施
Shuanggou water power station
diversion tunnel
measures of ice discharging