摘要
针对四台矿404盘区10#层与11#层属极近距离煤层,10#层已采空,掘进11#层5423顺槽穿越采空区时,压力显现明显,掘进非常困难的状况,通过采取一系列的先进施工工艺,顺利地实现了巷道的掘进,总结出了一套完整的极近距离煤层顺槽巷道掘进方法。
In the light of the situation that the 10^# coal seam and 11^# coal seam of 404 panel in Sitai Coal Mine belong to the extremely-short-distance coal seam, the 10^# coal seam has been worked out, and the tunneling of 11^# coal seam's 5423 crossheading through the worked-out section is very difficult because of the obvious pressure, by adopting a series of advanced tunneling methods, the tunneling works have been smoothly completed, and a series of the crossheading techniques under the worked-out section of the extremely-short-distance coal seam have been summed up.
出处
《科技情报开发与经济》
2005年第23期289-291,共3页
Sci-Tech Information Development & Economy
关键词
极近距离煤层
采空区
巷道布置
掘进技术
extremely-short-distance coal seam
worked-out section
tunnel arrangement
tunneling technique