工程项目进度与成本辅助控制横道图 被引量:8

The Controlling Bar Chart Good for Project Schedule and Cost
下载PDF
导出
摘要 将传统的横道图与网络计划技术相结合,并开发了一种新功能,使其不仅能做进度计划,还可在工程项目执行过程中进行“进度控制”,使计划进度根据三种不同的客观情况随时进行变更.该文还将施工过程中工程实际成本消耗引入横道图中,可清楚地显示出“完成了多少活,花了多少钱”,使工程项目管理更加清晰、方便. A new furction is developed by combining traditional gantt chart with modem net work technique, which not only helps to play a role in scheduling project but also in controlling schedule and cost in the process of carrying out the project. By using the new function, project schedule can be changed according to three actual conditions. The actual cost of project is also interpolated to gantt chart. Therefore,how much work has been finished and how much money has been expended can be found out, which makes the project management clearer and easier.
作者 刘津明
出处 《烟台大学学报(自然科学与工程版)》 CAS 2006年第1期68-73,共6页 Journal of Yantai University(Natural Science and Engineering Edition)
关键词 甘特图 项目进度控制 项目成本控制 甘特图新功能 gantt chart project schedule control project cost control new function of gantt chart
  • 相关文献

参考文献2

二级参考文献2

  • 1翁龙年 亢耀先.运筹学[M].北京:人民邮电出版社,1998..
  • 2Lawrence Bennett F, Lu Ming, Simjaan AbouRizk. Implified CPM/PERT simulation mode [ J ]. Journal of Construction Engineering and Management,2001 ( 11 ) :513-515.

共引文献27

同被引文献41

引证文献8

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部