摘要 文章通过计算,优化方案,采用人造基床作为钢套筒稳桩措施,解决了上海国际航运中心洋山深水港一期工程中码头嵌岩桩的难题。文中还对嵌岩桩施工中的钻机平台、成孔成桩、异常情况处理等作了简单总结。实践证明,人造基床方案是可行的,在施工进度、工程质量及经济上都有较大的优势,具有推广的价值。 With calculations and by optimizing the alternatives, artificial foundation beds are used as a measure to stabilize the steel sleeves, thus solving the difficult problems in building rock-socketed piles for the wharfs for the first phase of Yangshan Deep-water Port for Shanghai International Shipping Center. The paper also summarizes briefly the drilling platform, boreholing and building of piles as well as handling of abnormal circumstances. The engineering practice proved that the scheme of artificial foundation bedding is feasible and is more advantageous in ensuring the progress of the works and the engineering quality and also advantageous economically, worth generalizing.
机构地区 第三航务工程局
出处 《中国港湾建设》 北大核心 2005年第6期56-58,共3页 China Harbour Engineering
关键词 人造基床 稳桩 嵌岩桩 artificial foundation bed stabilization of pile sleeve rock-socketed pile
  • 相关文献

同被引文献8

引证文献1

二级引证文献4

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部