摘要
根据深圳地铁福民站地下连续墙工程实例,结合其施工工艺,分析地下连续墙工程合理的人工、材料、施工机械以及管理费等各项费用的组成,研究其合理的组价方法。
Based on the underground concatenation wall project of Fumin Station of Shenzhen Subway, in combination with the project's construction techniques , the cost composition of the underground concatenation wall project's reasonable manpower, materials, construction machines and managing expenditure is analyzed and reasonable composing exes are studied in this paper.
出处
《贵州工业大学学报(自然科学版)》
CAS
2005年第6期88-91,96,共5页
Journal of Guizhou University of Technology(Natural Science Edition)
关键词
地下连续墙
工、料
机消耗及各项费用
组价
underground concatenation wall
consumption of human power, materials and machines, and all other expenditures
composition