摘要
为了实现计算机对采掘计划的自动调整,在分析了采掘计划所有可能的调整情况的基础上,结合网络计划技术和评价采掘计划的直接指标体系进行研究,给出了一个计算机自动调整的算法,同时还研究了采掘计划工期调整的可靠性问题。还根据该方法编制了相应的软件,从现场使用情况来看,对于提高采掘计划编制工作的效率起到了一定的作用。该方法及其相关软件对矿井采掘计划管理和保证采掘计划的可靠性具有一定借鉴。
In order to adjust the mining-excavation plan automatically by computer, this paper analyzes all of the possibilities about the mining-excavation adjusting according to PERT technology, CPM technology and direct evaluation index system. The arithmetic of adjusting mining-excavation plan automatically by computer is then provided. Furthermore, this article studies the reliability about the adjusting project time of the mining-excavation plan. The plan of mining-excavation relay management system software has been developed based on this method. The efficient of management work has been improved since the software was used. The paper can have certain reference about mine mining plan management and guaranteeing the reliability of the mine mining plan.
出处
《辽宁工程技术大学学报(自然科学版)》
EI
CAS
北大核心
2005年第6期811-814,共4页
Journal of Liaoning Technical University (Natural Science)
基金
国家自然科学基金资助项目(50434020)
关键词
计划调整
采掘接替
回采
工期
可靠性
plan adjusting
mining-excavation relay
mining, working procedure time limit
reliability