现浇薄壁管桩(PCC)沉桩试验研究 被引量:1

Piling Test of Cast-in-place Thin-wall Concrete Pile
下载PDF
导出
摘要 现浇薄壁管桩是一种处理大面积软土地基的专利技术,研究历史相对较短。结合现浇薄壁菅桩在盐通高速公路及上海北环高速公路中的应用,通过现场试验对现浇薄壁管桩沉桩拔管速度、混凝土材料塌落度、沉桩过程对场地土性影响及沉桩挤土效应进行的研究,得出了优化的工艺技术参数;沉桩观测表明,现浇薄壁管桩存在一定的挤土效应,但在目前的设计间距下不会对邻桩构成影响,该研究成果对工程实践具有重要的指导意义。 PCC is a patent ground improvement technology. Relatirely the research history is short. A series of tests have been done to determine the reasonable concrete slump and pulling speed. The influence of piling to ground have been tested also. And the displacement monitoring during piling shows that the compaction effect of PCC is moderate, and the current pile space maybe eliminate such effects. The conclusions drawn in this paper are useful to the future projects.
出处 《东华理工学院学报》 2005年第4期354-358,共5页 Journal of East China Institute of Technology
基金 江苏省交通科技计划研究项目(02Y011)
关键词 现浇薄壁管桩 工艺试验 沉桩观测 cast-in-place thin-wall concrete pile piling test monitoring
  • 相关文献

参考文献1

  • 1[7]Kindel C E.1977.Mechanism of soil resistance for driven pipe piles.The 4th International Symposium of the Waterway[C].Coastal and Ocean Division of American Society of Civil Engineers,251~268.

同被引文献12

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部