摘要
本文介绍了低强度混凝土桩复合地基加固中有关监测内容、监测设备与监测时间进程。详细分析了低强度混凝土桩复合地基的桩、土应力及与荷载分担比、地基侧向变形与深度关系、地基沉降量与深度关系以及桩顶、桩间土表面沉降特点,实践证明低强度混凝土桩处理软土地基是可行的。
The testing contents, equipments and time progress for composite foundation with low-strength concrete pile are introduced, The stresses of the piles and the soil, the ratio of bearing load, the relationship between the lateral deformation of the soil and the depth, the relationship between the settlement and the depth, and the features of the settlement of the piles and the soil are analyzed in detail.
出处
《工程勘察》
CSCD
北大核心
2006年第1期34-38,共5页
Geotechnical Investigation & Surveying
关键词
低强度混凝土桩
软土地基
高速公路
low-strength concrete pile
soft clay foundation
expressway