摘要
针对工程施工进度网络计划中大量存在的搭接关系,提出了一种在计算机中存贮和计算搭接网络的方法,使得对具有搭接关系的网络图的描述十分简单、清晰,便于网络图计算、调整和优化的程序实现,对于网络计划技术的进一步推广应用有一定的实际意义。文中结合长潭高速公路第九标段施工网络计划给出了其中一个网络图存贮和计算的实例。
According to the overlapped relation of construction network in engineering, the author advances a method about the store and calculation in computer of overlapped network. It is very simple and clear for the describing about overlapped network and it is convenient for the program realization of calculating, regulating and optimizating about overlapped network. The method has a practice meaning for further application of network technology. In the paper, combining to the Changsha tO Xiangtan highway the ninth tender construction network plan, the author gives an example about the store and calculation of overlapped network.
出处
《长沙交通学院学报》
1996年第3期57-63,共7页
Journal of Changsha Communications University