摘要
介绍了石钢350m3高炉在停、开炉前的炉况准备工作及采用全焦开炉的方法,在确定合理的上下部调剂制度及迅速达产达效方面进行了成功的尝试。
The furnace operation preparation before blowing-in and blowing-out of Shigang' s 350m^3 Blast Furnace, and all coke blowing-in method are introduced in the paper, it is tried successfully both in deciding reasonable up & down regulating system and rapid reaching on output and efficiency.
出处
《冶金丛刊》
2006年第1期36-39,共4页
Metallurgical Collections
关键词
停炉
开炉
全焦
达产
达效
blowing-out
blowing-in
all coke
reaching on output
reaching on efficiency