摘要 在木兰溪前布墩水闸工程施工图设计时,针对复杂的地形、地质条件,分别采取浆砌石围堰、喷射混凝土防渗墙、钻孔灌注桩相结合等综合方法,保证闸室底板及消力池基坑开挖边坡的安全;采取桩基础解决闸室、公路桥基础土层地震液化以及它们之间的不均匀沉降问题,为该工程保质保量顺利完成奠定了的基础,取得了良好的经济和社会效益。 The treatment is expouned in the construction documents design of Qianbudun water Lock engineering in Mulan River. The sophisticated landform and geology condition are aimed. The integrated, methods laying stones cofferdam sprayed concrete impervious wall are drive-in compressed pile, The safety of lock floor and exeavatain slope in absorption basin are ensured. The foundation pile to solve the soil earthquake liquefacient in lock basin, wagon bridge foundation and to solve the nonuniform settlement between them are taken. The design laids a good foundation on the quality and quanity guaranteed of the engineering, and has made good economy and social benefits.
作者 姚建友
出处 《科学技术与工程》 2006年第4期503-506,共4页 Science Technology and Engineering
关键词 前布墩水闸 基坑开挖 基础处理 Qianbudun water Lock foundation ditch excavation foundation treatment
  • 相关文献

参考文献1

  • 1[1]中国建筑科学研究院.建筑基坑支护技术规程.北京:中国建筑工业出版社,1999.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部