提前修通兰新铁路双线疏乌段的主要经验

Main Experiences of Completing Shuwu Section of the Double一Track Lan—Xin Railway Ahead Of Sehedule
下载PDF
导出
摘要 提前修通兰新铁路双线疏乌段的成功经验是:有高效精干的组织机构及开拓务实的领导集体;制定并不断完善其施工进度总图,有效地控制了工期的进度;决策正确果断,采取了组织攻坚会战、倒排工期、人、机铺轨结合的有效措施;站场改造先抓试点,取得经验后,全面铺开;采用以劳动竞赛、工程项目承包负责制等激励手段,调动广大员工的生产热情;发挥双线指挥部各专业组室的职能作用,强化服务意识。 The successful experiences of com-pleting the Shuwu section of the double track Lan-Xin railway are as follows:. (1) there was an efficient and capable organization and a pioneering and practical leading group; (2) laying and improving continuously the construction progress chart, thus controlling effectively the construction progress; (3) making correct and resolute decisions, organizing mass campaign, setting construction schedules in reversed order, and laying track by both worker and machine; (4) carrying out pilot program of yard renovation first, and then implementing widely; (5) adopting encouragement mechanism, such as emulation campaign and project contract system to bring the enthusiam of workers into play; and (6) playing the role of each division of the project headquarters and strengthening service function.
作者 邓永周
出处 《铁道运输与经济》 北大核心 1996年第3期10-13,共4页 Railway Transport and Economy
关键词 兰新双线 建设 例排工期 站场改造 铁路 double track construction of Lan梄in rail-way, setting project schedule in reuersed order, yard rerova-tion, service concept.
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部