某银行营业楼由于临近地下管道施工引起不均匀沉降,造成倾斜超过国家规定标准,需进行加固纠偏处理。采用锚杆静压桩结合掏土法进行加固纠偏,加固效果可靠。此外,对由锚杆静压桩施工引起的附加沉降应给以足够的重视。
A bank building needs reinforcement and rectification because of uneven settlement caused by vicinal construction of underground pipeline. The application of static bolt-pressing piles and digging is introduced in this project. Moreover, it is necessary to emphasize the subsequent settlement caused by construction of static bolt-pressing piles.
出处
《低温建筑技术》
2006年第1期62-63,共2页
Low Temperature Architecture Technology
关键词
锚杆静压桩
掏土法
加固纠偏
附加沉降
static bolt-pressing piles
digging
reinforcement and rectification
subsequent settlement