摘要
在厂房技术改造中,由于采用了钻孔灌注桩加固基础的施工方案,解决了在软弱地基土层加固柱基础的难题,以及生产与施工的矛盾.
This paper introduces the construction scheme of cast-in-place pile for strengthening column footing.This scheme not only successfully solves the contradiction between production and construction,but also provides a dependable channel for future technology reconstruction about old factory building.
出处
《工业建筑》
CSCD
北大核心
1996年第5期12-15,共4页
Industrial Construction
关键词
工业厂房
钻孔灌注桩
软土地基
柱基础
factory reconstruction
soft foundation
cast-in-place pile,grouting compaction