摘要
大江截流是三峡工程网络计划中关键路线上的控制点,也是一二期工程的转折点,其成败关系重大。要实现1997年大江高质量截流,必须根据大江截流的特点、截流时段和截流流量标准、施工期通航等问题对大江截流关键技术问题进行正确决策。
The TGP river closure which is the controlling point on the critical paths of TGP construction networks and the turning point of Phase- 1 and Phase- 2 construction will be extremelycritical to the smooth progress of TGP construction. Sound decisions and proper approaches have to be made and adopted to deal with the critical technical issues concerning for the river closure on the basis of such features as the occurring time, flow discharge,and non - suspension of navigation during the river closure so that the successful' river closure with high qbality can be achieved.
出处
《中国三峡建设》
1996年第6期6-8,共3页
China Three Gorges Construction