摘要
重点介绍了通过斜井施工的长大隧洞出渣系统设计。其主要内容为采用有轨运输的斜井施工出渣形式设计,机械设备的配套及主支洞交叉段井底渣仓的设计。
The design of the spoil disposal system for the construction of the large and long tunnel tunneled through the inclined shaft is described emphatically herein, which includes the design of the spoil disposal through the inclined shaft with the railed transportation and the designs for both the arrangement of the machineries and the spoil bunker at the crossing of the main tunnel and the shall.
出处
《水利水电技术》
CSCD
北大核心
2006年第3期18-19,共2页
Water Resources and Hydropower Engineering
关键词
斜井
有轨出渣
有轨输送
提升机
井底渣仓
inclined shaft
spoil disposal
tracked transportation
lift
spoil bunker