本文以福建大唐宁德电厂一期海水循环冷却水泵系统工程为例,分析大型沉井在软弱土层中施工的难点及关键技术问题。
This article analyzes the difficult points and key technology of the large - scale open caisson constructing in weak soil layer through the first stage project, constructed by datan - ningde electric power plant in Fujian province, of cooling water pump system with sea water.
出处
《福建建筑》
2006年第2期106-107,111,共3页
Fujian Architecture & Construction
关键词
大型沉井
软弱土层
施工
关键技术
Large - scale open caisson, weak soil layer, construction, key technology