摘要
为优化构皮滩拱坝中孔预应力闸墩锚索永存张拉吨位,首先采用方案优选的方法确定主次锚索永存张拉吨位组合,但优选结果拉锚系数偏大,再对闸墩体型进行优化,然后采用基于参数化有限元的ANSYS优化设计模块对主次锚索永存张拉吨位进行优化,优化结果满足应力控制要求,降低了拉锚系数。
In order to optimize the perpetuation tensioning tonnage of prestressed pier anchor wire of Goupitan arch dam, first the scheme contrast method is adopted to define the perpetuation tensioning tonnage combination of the primary and secondary anchor wire, but the optimization result is that the pull-anchor coefficient is too big; then the body form of the pier is optimized; finally the anchor wire perpetuation tensioning tonnage is optimized by using ANSYS optimization design module based on parametric FEM, the optimization result is acceptable and the Pull-anchor Coefficient is lowered down.
出处
《红水河》
2006年第1期29-32,共4页
Hongshui River