介绍了吴城水库的工程概况,指出了工程存在的较严重的一系列安全隐患问题,提出了加高培厚大坝、增设溢洪道控制闸门、坝体坝基灌浆等除险加固措施。
This paper introduces the general engineering situation of the Wucheng Reservoir, points out a series of more severe incipient faults existing in this engineering, and puts forward some ganger-eliminating and reinforcing measures such as heightening and thickening the dam, building the new control anchor gate on the spillway, and grouting the dam body and dam base, etc.
出处
《科技情报开发与经济》
2006年第4期283-284,共2页
Sci-Tech Information Development & Economy
关键词
除险加固设计
灌浆防渗
帷幕灌浆
黏土灌浆
吴城水库
ganger-eliminating and reinforcing design
watertight groutin
curtain grouting
clay groutin
WuchengReservoir