In this paper we consider a single-machine scheduling model with deteriorating jobs and simultaneous learning, and we introduce polynomial solutions for single machine makespan minimization, total flow times minimization and maximum lateness minimization corresponding to the first and second special cases of our model under some agreeable conditions. However, corresponding to the third special case of our model, we show that the optimal schedules may be different from those of the classical version for the above objective functions.
In this paper we consider a single-machine scheduling model with deteriorating jobs and simultaneous learning, and we introduce polynomial solutions for single machine makespan minimization, total flow times minimization and maximum lateness minimization corresponding to the first and second special cases of our model under some agreeable conditions. However, corresponding to the third special case of our model, we show that the optimal schedules may be different from those of the classical version for the above objective functions.