摘要
在分析新建铁路工程施工用电特点的基础上,提出合理选择施工用电容量及电源方案,采取临时和永久性电力线路相结合的方式,严格控制临时用电规模,降低工程投资,实现合理优化建设工程资金的目标。
On the basis of analyzing the power use character of new railway engineering, the paper brings out the programme of rational selecting power capacity and power sources. It can adopt the combined manners of temporary and permanent power lines, control the temporary power use engineering scale, decrease investment and realize the aim of optimal engineering funding.