通过现场考察、原型观测和有限元计算,分析了拦污栅断裂的原因,提出了技术改造的建议。
The cause of cracking of the trash-rack at the intake of Wangfuzhou hydropower plant is found out by vibration measunement and investigation on the spot and by finite element analysis, some opinions about technical reform for the trash-rack are proposed.
出处
《湖北水力发电》
2006年第1期14-16,共3页
Hubei Water Power
关键词
王甫洲水电厂
拦污栅
断裂