摘要
南芬露天铁矿新火药加工厂设计、施工后,在试生产过程中发现 原设计的地面设施存在许多技术问题,需进行改造设计,并研制相应的设 备。改造后达到了正常生产的要求,为火药加工厂按时搬迁、保证矿山扩 帮工程的顺利进行创造了条件。
After designing and constructing a new explosive processing plant in Nanfen surface iron mine,there are many technical problems on the ground installations designed originally,which were found in the process of trial production,thus it is, necessary to perform the reforming design and develop the relative equipment. The mormal production requirements were met after reforming. The conditions were provided for removing the explosive processing plant in time and ensuring the wall slash working to be performed smoothly.
出处
《矿业研究与开发》
CAS
北大核心
1996年第1期48-50,共3页
Mining Research and Development
关键词
炸药加工厂
技术改造
扩帮工程
地面设施
Fxplosive processing plant, Technical reform, Wall slash working