摘要
近十多年来,随着我国市场经济的不断完善和水电技术管理水平的提高,相继建成了一批投资省、工期短的水电工程。在目前水电大开发的有利形势下,重新认识水电工程的建设工期,具有重要的现实意义。建议水电工程在实施过程中,应妥善处理好进点开工时间与环保审批时间的关系、截流时间与移民安置的关系,解决好提前发电、机组订货、临建投入等问题。
In the recent decades, with the increasing improvement of market economy and managing abilities of hydropower technology in our country, some hydropower projects with low cost and short construction period have been built in time in succession. Under the present favorable situation of hydropower development, it has great significance to reconsider the construction period of hydropower project. It is proposed that developer of the hydroelectric project should, in the course of implementing, handle properly the relationship between the time of commencement
and date of approval of environmental assessment report, between the time of river closure and relocation, the issue of advanced generation, order of generating units and front-end investment.
出处
《水力发电》
北大核心
2006年第3期1-4,共4页
Water Power
关键词
水电工程
建设工期
管理水平
hydropower project
construction period
managing abilities