钢管桩打拔桩施工研究 被引量:3

Construction Research of Pipe Pile'Driving and Extracting
下载PDF
导出
摘要 文章结合杭州湾跨海大桥南岸滩涂区的工程地质和施工特点,针对栈桥基础钢管桩的打入和拔出方案进行了比选;对振打设备的选择,应用了振动沉桩计算理论,对该理论进行了分析验证,成功解决了滩涂施工中钢管桩打入和拔出的技术难题,有力保证了南岸栈桥施工的快速顺利进行。 In the combination with the engineering geology and the construction features of the mudflat area on the south bank of the oversea bridge in Hangzhouwan,the paper makes comparison of the pile driving and extracting themes to the pipe foundation of the landing stage .In the selection of the shaking equipment, the vibrosinking theory is applied and it is also through the analysis of this theory, the difficult technical problem of the driving and extracting piles in mudflat area is solved, the rapid and successful construction of the landing stage on the south bank is effectively ensured.
出处 《安徽建筑》 2006年第2期74-76,共3页 Anhui Architecture
关键词 钢管桩 打拔桩 施工研究 pipe pile driving and extracting piles construction research
  • 相关文献

参考文献1

  • 1日本建筑学会建筑钢桩基础设计规范.

共引文献1

同被引文献12

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部