摘要
马钢南山铁矿凹山采场排水斜井的延伸工程涌水量大、岩体破碎、地质条件复杂。在施工斜井中采用了强化排水、强化临时支护、处理悬顶和光面爆破等工程技术措施,确保工程的施工质量和进度,平均掘进速度由6.50m/月提高到12.43m/月,取得了较好的效果。
The extended engineering of a inclined shaft to be use for drainage,which is located atAoshan Mining District of Nanshan Iron Mine,Maanshan Iron and Steel Company,is sinked in the stratum of larse now of water,broken rock-body and complicated geological condition. In the process of construction, the technical measures such as strengthening drainage, strengthening temporary support,treating hanging-up roof and smooth blasting etc. are used. The quality and progress of whole engineeingis ensured,the average sinking speed is increased from 6. 50m to 12. 5m per month.
出处
《金属矿山》
CAS
北大核心
1996年第4期22-25,共4页
Metal Mine
关键词
涌水量
破碎岩体
斜井
超前支护
施工技术
Flow of water, Broken rock-body, Inclined shaft, Advanced support