摘要
龙滩水电站大坝混凝土浇筑强度最高时达10.5万m3/月,致使原有混凝土入仓设备已不能满足施工需要。在坝后的有限空间内,增设了高速皮带机等入仓手段,大大提高了混凝土的浇筑强度。
The max. concreting intensity of the Longtan hydroelectric project will be as high as 105,000cu.m/month. So the present concrete placing equipment will not be able to meet the requirement of the project work. Therefore the high-speed belt conveyors have been added at the limited space behind the dam, which have greatly inereascd the concreting rate.
出处
《水力发电》
北大核心
2006年第4期52-53,57,共3页
Water Power
关键词
常态混凝土
混凝土入仓
高速皮带机
龙滩水电站
normal concrete
placement of concrete
hlgh-speed belt conveyor
Longtan Hydropower Station