既有线斜交框架中继间顶进施工技术

CONSTRUCTION TECHNIQUE OF JACK-IN BETWEEN JUNCTIONS OF SKEW FRAME FOR EXISTING RAILWAY LINE
下载PDF
导出
摘要 研究目的以胶济电化工程DK253+185.267m+14m+7m辛化路立交框架桥施工为例,介绍了在维持既有运营的情况下,对斜交分段式框架施工方法的多方案比选后,确定采用中继间顶进的施工方法进行施工。研究方法对中继间顶进法施工中的顶进后背设计、斜交转正块设计、滑床的处理、线路加固及临时墩设计、顶进方向控制等技术要点进行了详细的阐述。研究结果在施工过程中对上述技术要点的控制,该桥整个施工时间只用了135d,分段框架前后相错量控制在5mm以内,安全、优质、快速地完成了该桥施工。 Research purposes: Taking the construction of Xinhualu Flyover Frame Bridge at DK 253 + 185. 267 m + 14 m +7 m in Jinan -Yantai Railway Electrification Project as an example, it was decided to adopt the construction technique of jack -in between junctions while keeping the line open to traffic, after comparing many schemes for construction of skew sectional frame. Research methods: The technical points are described in details of jack - in design of rear back, design of skew inverting block, designs of sliding bed treatment and track strengthening, design of temporary pier and control of jack - in direction for the construction conducted by adopting method of jack -in between junctions in this paper. Research results : It only took 135 days to finish construction of the bridge quickly with features of safety and high quality due to control of the technical points mentioned above during construction. The tolerance was within 5mm between the front end and rear end of sectional frame.
作者 任宗军
出处 《铁道工程学报》 EI 北大核心 2006年第2期33-38,共6页 Journal of Railway Engineering Society
关键词 斜交框架 中继间顶进 转正块 后背 线路加固 施工技术 skew frame jack - in between junctions inverting block rear back track strengthening construction technique
  • 引文网络
  • 相关文献

参考文献5

  • 1中铁三局.铁路桥涵施工技术手册、桥涵[S].北京:中国铁道出版社,1999.
  • 2铁道部第三勘测设计院.铁路桥涵设计基本规范[S].北京:中国铁道出版社,1991.
  • 3铁道部.铁路技术管理规程[S].北京:中国铁道出版社,1999..
  • 4重庆建筑工程学院,湖南大学.结构力学[M].北京:人民教育出版社,1983.
  • 5李克钏.基础工程[M].北京:中国铁道出版社,1993..

共引文献5

;
使用帮助 返回顶部