摘要
结合施工过程,应用三维有限单元法,对龙滩大坝连续浇筑混凝土的温度及温度应力,进行仿真计算的研究。论述了加快施工进度,连续上升浇筑混凝土的可行性,必要条件及需要采取的温控措施。
Based on the actual construction, a study on the simulative calculation for both the temperature and the thermal stress of the continuous RCC placement for the construction of Langtan RCC Gravity Dam is made with 3-D finite element method. The feasibility, necessary condition and the measures for the temperature control for the continuous placement to speed up the construction progress is discussed herein as well.
出处
《水利水电技术》
CSCD
北大核心
2006年第5期59-62,共4页
Water Resources and Hydropower Engineering
关键词
龙滩碾压混凝土重力坝
RCC连续浇筑
温度场
温度应力
温控
防裂
Longtan RCC Gravity Dam
continuous RCC placement
temperature field
thermal stress
temperature control
crack control