摘要
通过碾压试验、施工复核及大坝运行观测,得到了大坝的设计填筑标准,从而确定了经济合理的压实方法,包括压实机械选型、机械参数、砂砾料加水量等。同时,制订了压实质量控制方法,研究和改进了填筑的施工工艺和措施,优化了大坝体型及施工碾压参数,节约了投资。
Based on the roller-compacted test, check on construction and observation during operation, the fill-criteria of the design for the dam is obtained, and then the economic and reasonable roller compacted method, including selection of the roller, mechanical parameters, watering amount for material of sandy gravel etc., is determined as well. Simultaneously, the quality control method for the compaction, the construction technologies and measures and the roller-compacted parameters are studied and optimized, in this way the investment is saved at last.
出处
《水利水电技术》
CSCD
北大核心
2006年第5期83-84,88,共3页
Water Resources and Hydropower Engineering
关键词
希尼尔水库
砂砾石均质面板坝
碾压质量
坝体稳定
Xinier Reservoir: concrete face sandy gravel-till dam
rolling compacted quality
stability of dam