摘要
以北京市和广州市轨道交通工程为例,详细介绍了大吨位整孔预制箱梁预制和架设的概算编制方法,指出机械地套用地方市政定额是不科学和不切实际的,应根据工程的具体工艺工法借用铁路工程定额,达到合理确定工程造价的目的。
Taking the rail transit projects of the cities of Beijing and Guangzhou for example, this article gives a detailed description of the methodology of budget estimate making for the prefabrication and erection of full span box girders of heavy tonnage before pointing out that it is not practical nor scientif- ic to blindly copy the ratings of local municipal works. Whereas the railway engineering norms should be borrowed so as to achieve the end of reasonably determining the engineering cost according to the specific technology and construction methods employed.
出处
《铁路工程造价管理》
2006年第3期42-44,共3页
Railway Engineering Cost Management
关键词
整孔箱梁
预制架设
模板
吊装机具
设计概算
Full span box girder, fabrication and erection, form, lifting rig, budget estimate of design