摘要
根据上海轨道交通8号线的实践经验,对地铁基于通信的列车控制(CBTC)系统工程设计中需要注意的几个具体问题,如:辅助轨旁系统的选用、轨旁无线设备的安装方式、轨旁无线接入点设备的供电方案、骨干通信网的选择等进行了讨论,并给出了解决建议。
Based on the experiencs of CBTC (communication based train control system) adopted in Shanghai urban rail transit Line 8, the author analyzes the critical issues for the design and installation of CBTC, such as the selection of the auxiliary trackside systems, the installation of the access points, power supply solution for APs, the main network selection, and discusses some possible solutions for these issues.
出处
《城市轨道交通研究》
2006年第5期48-50,共3页
Urban Mass Transit
关键词
基于通信的列车控制
工程设计
轨旁系统
轨旁无线设备
communication based train control, design and installation, trackside systems, trackside radio communication equipment