一项石油单井工程的施工建设涉及到许多方面,本文从单井项目成本、工期、质量、环境影响和安全健康五大方面进行了分析;建立了单井工程项目综合评价指标体系和综合评价模型;给出了指标和权数的确定方法;并运用模糊数学的原理对单井工程项目进行了模糊综合评价,结合单井工程实际进行应用。
A single well petroleum project construction involved so many aspects. This article analysed in five big aspects, which were single well project's cost, the time limit for a project, the quality, the environmental effect and the security health. It established a synthetic evaluation system of the single well engineering project; And we also produced a method to get the index and weight; Moreover in terms of the fuzzy mathematics principle,we gave a fuzzy syrithetic evaluation to the single well engineering project, and applied it in reality.
出处
《内蒙古石油化工》
CAS
2006年第5期189-191,共3页
Inner Mongolia Petrochemical Industry
关键词
单井工程
成本
质量
工期
环境影响
安全健康
综合评价
Single well project
Cost
Quality
Time limit for a project
Environmental effect
Security health