介绍了泰山300MW核电机组全范围仿真机的测试验收的整个过程,包括:验收测试规程的形成,工厂内部预测试和工厂用户测试。并分析了测试验收过程中存在的重大问题及解决的办法。
The paper introduces the whole acceptance test procedure of Qinshan 300MW Nuclear Power Unit Full Scope Simulator.The following stages are included:formation of Accep tance Test Procedure documents;preacceptance test of the simulator in factory;Accep tance Test of the simulator in factory,The main problems in acceptance test procedure and measures for solving them are analysed.