期刊文献+

龙滩水电站施工规划设计的几个问题 被引量:2

Several problems in construction planning and design of Longtan Hydropower Station
下载PDF
导出
摘要 龙滩水电站主体工程建设共分为5个标。其施工导流选用隧洞导流方式,围堰采用碾压混凝土过水围堰,挡水标准为10年一遇,挡水流量14700m3/s,该围堰拟由承包商设计,挡水标准可适当降低。经方案比选,施工总进度采用7年半发电方案。大坝混凝土量约601万m3,主要浇筑期41个月,选用进口高速皮带机运输上坝,仓面塔式布料机浇筑为主,缆式起重机为辅的混凝土运输浇筑方案。 The main project construction of Longtan Hydropower Station will be divided into 5 bids. The construction diversion will be tunnel diversion. The cofferdam will be RCC overflow cofferdam with retaining standard of ten-year flood and retaining discharge of 14 700 m3/s. This cofferdam is planned to be designed by the contractor and then the retaining standard could be lowered properly. Based on comparation and selection,power generation of the station will be 7. 5 years after the construction commencement,which has been adopted in the total construction progress. The volume of dam concrete will be about 6. 01 million m3. The main pouring period will be 41 months. The imported high-speed belt conveyor will be used. The concrete pouring plan will take tower unloader as main and take cable crane as supplementary.
出处 《水力发电》 北大核心 1996年第6期47-50,共4页 Water Power
关键词 水电站 工程施工 规划设计 寻流隧洞 Longtan Hydropower Station,construction planning and design,civil works,sub-contract proposals, construction diversion,overall program,dam construction
  • 相关文献

同被引文献6

  • 1王真民.构皮滩水电站施工规划[J].贵州水力发电,2004,18(6):39-43. 被引量:2
  • 2DL/T5397.2007,水电工程施工组织设计规范[S]..
  • 3中国电建集团昆明勘测设计研究院有限公司,戛洒汀一级水电站可行性研究报告[R].2015.
  • 4JDL/T53972007水电工程施工组织设计规范[s].
  • 5中国电建集团昆明勘测设计研究院有限公司,戛洒江一级水电站可行性研究报告[R].2015.
  • 6韦卓信,彭茂雄.百色水利枢纽工程施工规划设计[J].广西水利水电,2002(B10):63-68. 被引量:3

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部